Project Schedule

The below are proposed dates for the Biltmore Preparatory Academy renovations.
  • Board update - September 18, 2018
  • GMP (Guaranteed Maximum Price) Approval - October 2, 2018
  • Start Construction - October 22, 2018
  • Start Multi-Purpose Building - May 1, 2019
  • Complete Gym - May 3, 2019
  • Demo Main Parking Lot - May 24, 2019
  • Mulit-Purpose Building and Parking Lot Complete - August 2, 2019